Please be advised that the City of Richmond Hill will be undertaking road reconstruction works on Maple Grove Avenue and Wendy Way.


Upcoming Key Schedule

  • Mid‑March 2026: Construction start

  • Late 2026: Substantial completion of underground works

  • Summer 2027: Substantial completion of surface road works


Construction schedules are subject to change due to weather or site conditions.


Residents will be notified of any significant changes as work progresses.


For questions or concerns contact: Kyle Paterson, Project Manager T: 905-747-6341 E: kyle.paterson@richmondhill.ca


Construction notice for Maple Grove Ave and Wendy Way. Work starts mid-March 2026. Includes a project map and text details for residents.
Construction notice for roadwork in Richmond Hill. Details on ditches, contacts, and project locations. Includes a QR code and website link.
Diagram of a sump pump outlet system with labeled parts, including pipes and check valve. Text: Richmond Hill construction notice.

 
 
bottom of page