top of page

Update: Air Management Facility - Oak Ridges Smell

  • Marian
  • Jan 14
  • 1 min read

Updated: Mar 14

Update March 5, 2025

Since the last update, they have been able to receive and install overhead traveling crane systems. They also received the generator exhaust stack and moving forward with installation of it.

Photo courtesy of York Region
Photo courtesy of York Region

Most of the work is now limited to the facility interior where the Region’s contractor continues to progress in preparation for commissioning currently anticipated for Summer 2025.


Update January 14, 2025

As you may remember, York Region started building an air management facility near Yonge Street and King Road in the Fall of 2022. This facility aims to eliminate the unpleasant odor that has persisted in the area for years.


At this time, the building envelope has been completed and our contractor is working to finalize the internals prior to testing and commissioning the facility.


For a detailed update, please see the summary below:         

Two items listed above are ongoing as result of market supply shortages and delays – this includes the generator exhaust stack and overhead traveling crane system. These items are well beyond their original scheduled delivery date. To help move these items along, the Region’s contractor and consultant are diligently working with the suppliers.

 

Testing and commissioning is also behind the schedule mainly due to delay in Hydro connection to the facility which was connected very late last year (Dec 2024).

 

They are currently aiming to complete the system testing and facility start up by end of April 2025.

 

They are continuously working to move the project along and commission the facility to resolve the odour concerns in the Oak Ridge’s community.


bottom of page